Do you know what EAC is or what it stands for? Are you wondering to know or access the most effective formula related to EAC? Well, right now, you are at the right place. This article can easily find all the essential information about EAC.
The calculation process helps estimate the project's total cost if we talk about the Estimate at Completion. The main use of EAC is on the project cost estimate at completion that has been started.
There is no doubt that EAC has excellent service in the organization as it helps the team member calculate the estimated cost of the project. Estimates at completion in project management play a vital role as the fundamental progress factor relies on it.
Click to read more about Project Management Lifecycle.
We all know that it is important to understand the total cost or total spent money on the project. It is not easy to calculate the entire cost like standard methods as the calculations are very lengthy. To make the math easy, Estimate at Completion is essential. For that, you need to stick to this article till the end to grab all the required processes.
EAC corresponds with the project cost estimate at completion, which estimates the total cost in the planning phase. Considering the total price after completing projects and the BAC is essential based on the assumptions and estimates.
The calculation process is very different, and it requires a lot of skills and experience.
If you are new to these calculations, you need to learn all the steps with project cost estimates at completion before implementing them in your project. It is highly suggested to know all the required steps to proceed with the method of EAC, or we can say estimate at calculations for better results.
Before going further, it is essential to know that an assumption or estimate on the project's cost and schedule needs to be made. The four critical basic assumptions are the following.
- The first assumptions include the project performing at the budgeted rate. The project must be at the budget level to avoid further loss or damage risks. Make sure to implement these assumptions to secure better results.
- One of the assumptions is an estimate to complete the assumptions.
- The second most important assumptions are the future performance, and it should be in line with the present cost variance with the cost performance index.
- The future of the performance will also be in line with the present cost performance index and their schedule performance index.
One of the best process areas we frequently use to help our clients, even with establishing the time-phased estimate to complete ETC data, is to create credible estimates at the completion EACs during the execution phase of a project. This ETC date aims to provide the main realistic plan to complete all the remaining work.
They add all the cumulative to the actual date of its cost to all the evaluations to make it complete. They also manifest the total expenditure for all the projects with an approximate project cost estimate at completion.
EAC is used to be compared to the central budget at completion BAC even at several levels of its complete details to identify its areas and analyze.
The estimate at the completion always matters there; it also represents the real money. But there are also some questions about whether the company profits from these contracts. So, you should know that exceeding the price of a contractual target always creates some financial liability for the company.
But, the magnitude of liability should always be noteworthy, which depends on the value and the type of contract.
You may have already seen in many other companies that when the actual price of any company is consistently higher than anticipated, this has a cumulative negative impact on the company's balance sheet. The root which always causes those negative impacts then customarily starts in the phase of its proposal.
Just like before, there is still some lack of access in these proposals to all the historical data and all, or it also gets unable to put them together with any perceptible backup data so you can produce the data-driven, verifiable basis of all those estimates which they have with the quality proposal estimates even continually.
If we talk about any other instances, their companies always choose to price their proposal to easily win the work even after knowing that they might lose money on the contract, but at least they got a win.
Every company has always made sure to keep the best-case scenario, even if they have a lot of data to dictate it quickly if they have any chances to make a significant profit or not, and they decide to take some losses. Still, they also do many calculations to project cost estimates at completion with the overall strategy of their business.
When the company is fully prepared to produce proposals even with the higher quality, data-driven basis of estimates, they also have the foundation to build a realistic and executable budget baseline after the contract award. Suppose they have the best budget plan and provide a more accurate model of its performance and the actual costs incurred.
In that case, this also helps them increase the likelihood of the company's target of profit margins and finally meet a project cost estimate at completion.
Check this course to learn more about such challenging aspects of a Project Manager’s career with a Certified Associate in Project Management (CAPM) Certification Training course.
As you know, producing any data-driven based on any estimate and creating feasible baselines of its budgets always takes some effort. Proposal and project control teams both need this observable process to follow all those supported with the right tools, which also help them to do their job more appropriately.
- The most proper way to maintain all the estimates is to complete the provided visibility into their current schedule. Cost factors, emerging risks, and realized, resource requirements to make it achieve all the project objectives and meet its financial goals.
All these things help the project manager to make timely and informed decisions.
- All these parties should be more aware of any situation where the estimate to complete and estimate at completion exceeds the funding profile. Even the Management needs to be mindful of all kinds of potential impacts on the anticipated profit margin for the project.
Now, let's explore more about each estimate at completion. Mainly the term estimate of calculations is the forecasting technique primarily employed to estimate the project's cost after the project.
The best thing about estimating estimates at completion is that it helps measure how much a project may be off track. It also allows the team member to inform the most appropriate corrective changes.
Generally, there are four practical ways to calculate the project cost estimate at completion quickly. You can easily use the formula to make your calculations easy. Every unique formula is used for the specific scenario and considers different factors. It is essential to know the entire procedure of project cost estimate at completion in detail with examples.
Consequently, you don't need to brood here and there searching for information. You need to read this article to know all the essential formulas.
The first basic formula with a project cost estimate at completion is quite challenging for beginners. However, you will learn after having some experience. Whenever the future financial performance of the project is expected to be similar to the project's past performance, then the estimate at completion can be easily calculated with the help of the cost performance index.
The first formula includes the calculations with the cost performance index, also called CPI. The cost performance index helps indicate how a project is performing regarding the costs. The analysis of the cost performance index is to earn value divided by its actual costs.
Earned value is donated by EV, and it is the estimated cost at a particular stage in the project. AC denotes the actual costs, and it is considered the essential expenditure of the project at that specific stage. To calculate each, you need to rely on the following formulas.
The formula for the CPI is like this:
Cost performance index (CPI) = Earned value (EV) / Actual cost (AC)
It is the first estimate at the completion formula. You can calculate the value by putting the number on the procedure. For that, you need to put the earned value and actual cost to get the results of the cost performance index. When the assembled value is equal to the actual price, then the calculations of the cost performance index will be similar to 1.
It means that the project is on track as it should be. If we talk about the budget at completion, it is considered the original budget estimate created at the start of the project. The formula assumes that the future of any specific project's financial performance will be the same as the project's past performance.
It will give you a rough idea of the budgeting process to ensure the changes or progress of the project. The project's progress will directly show a positive impact on the organization's growth.
Now it is essential to know the accurate formula of estimate at completion, and it is calculated as budget at completion calculation divided by the cost performance index.
The formula for the calculations of Estimate at Completion is as follows:
Estimate at completion (EAC) = Budget at completion (BAC) / Cost performance index (CPI)
For example: when project A has an estimated budget of around $100000 and the cost performance index is 0.8. The project manager believes that the project's past performance will also mirror the future performance.
Here are the calculations:
Estimate at completion = Budget at completion (BAC) / Cost performance index (CPI)
Estimate at completion = $100,000 / 0.8 = $125,000
Consequently, the estimate at completion would be $125,000.
Formula Two
Now let's talk about the second most preferred formula for calculating estimates after project management. You can use formula number two when the project went off track due to any reasons or aspects. The main objective of formula 2 is to give an accurate report regarding the project going off track.
This formula helps calculate the estimate at completion, or EAC, by adding the actual cost to the difference between the budget at completion and its earned value. This formula assumes that the rest of the project will follow the process as planned. Formula 2 to calculate EAC is like the following:
Estimate at completion (EAC) = Actual cost (AC) + (Budget at completion (BAC) - Earned value (EV))
You can use this formula for the calculations of estimates at completion. For that, you need to put the value of the actual cost and budget at completion. It is also essential to know the earned value to complete the calculations. Put the value to know the results.
Example: Suppose project B went off track somehow on any specific task. Reasons can be multiple. However, project Y has a budget at completion of around $100,000, and its earned value is approximately $30,000. After that, the actual cost was found to be $35,000. The rest of the tasks are expected to be on track with the budget of the original task.
Here are the calculations:
Estimate at completion (EAC) = Actual cost (AC) + (Budget at completion (BAC) - Earned value (EV))
Estimate at completion (EAC) = $35,000 + ($100,000 - $30,000) = $105,000
Consequently, the estimate at completion would be $105,000.
Formula Three
If we talk about the estimate to completion formula three, it is pretty easy for the calculations. Even a beginner can easily use this formula to calculate the expected results. There is no hidden fact that a project can be behind schedule and over budget at certain times. There may be some specific or uncommon reasons.
However, logic doesn't matter. We have to see the calculations of the estimate at completion. Cost and schedule will be considered in these instances while the estimate calculations are completed. It will help get better information to make progress next time in the project.
To begin with formula 3, it is essential to include a schedule performance index denoted by SPI. The schedule performance index mainly indicates how behind your project is or how ahead a project is compared to the planned schedule.
The value of the schedule performance index can be calculated by dividing the earned value by the intended value. PV denotes the intended value, and it is the actual value of the work done that has been done on the given schedule. The formula for the calculations of schedule performance index or we can say SPI as follows:
Schedule performance index (SPI) = Earned value (EV) / Planned value (PV)
Though the formula is straightforward, you must know the accurate earned and planned values to get the exact schedule performance index. The value of the schedule performance index will give you brief ideas about the project's deadline to know the progress level.
It is essential to use these calculations to get better results. You will fix the work done according to the schedule to increase productivity. Estimate at completion calculator will give you accurate results and value.
That is where the proper interaction, techniques, and devices can help proposition groups and undertaking control groups make the best choice. A past blog, Benefits of an End-to-End Solution for Proposal and Earned Value Management, strolls through the method of delivering an information-driven quote, rapidly laying out the financial plan benchmark after agreement grant utilizing the quote information effectively progressing to the execution stage, and overseeing gauge changes.
Keeping up with the gauge of project cost estimate at completion to finish information is similarly significant to making that underlying spending plan information. Try to keep it as simple as possible.
Keeping up with the ETC should be a standard piece of the status and investigation cycle to guarantee the time staged ETC information mirrors the current timetable, updates to asset tasks, activities executed to deal with chances, and endorsed changes.
It helps the undertaking administrator since they have undeniable detailed source information for the work components. They can then survey different elements affecting the task level gauge at the finish, like changes in upward rates.
The main objective of the EAC is to take the incurred costs and earned value into account. Additionally, this observed value is added as the estimated amount of the expected work or the cost requirements to complete the entire project.
It additionally assists with forestalling unsavory monetary threats for upper-level administration. The executives can regularly work out benefits and misfortune edges on the venture with reliable information or arrange activities.
Even complex calculations like EAC is all in a day’s work for a project manager, and if you are someone driven by challenges. Take a look at PMI certification training courses from Sprintzeal.
Issue Log in Project Management - Uses and Importance
ArticleSupply Chain Response And The Factors Involved In It
ArticleBest Agile tools for Project Managers in 2023
ArticlePMI-PMP® Exam Changes 2021 Explained in 5 Minutes
ArticleProject Initiation Phase - Importance and Roles Involved
ArticleDelphi Technique and Its Role in Project Management
ArticlePMBOK Guide and Project Management Certification Updates 2022
ArticleHow to Use Google Calendar as a Project Management Tool
Article10 Reasons Why You Should Get PRINCE2 Certification in 2022
ArticleCAPM Cheat Sheet 2023
ArticleCAPM Certification Study Guide
ArticleCAPM Certification Exam Preparation Guide 2022
ArticleTop Benefits of CAPM Certifications
ArticleGuide to Advancing Project Management Career with PMP Certification
ArticlePMP Vs PRINCE2 - Which Project Management Certification is Better?
ArticleProject Management Interview Questions and Answers for Managers
ArticleProject Management Software to Use in 2023
ArticleBest project management certifications in 2023
ArticleProject Feasibility Study in Seven Steps
ArticleCAPM vs PMP – which project management certification is better?
ArticleProject Scope Management Guide 2023
ArticleProject Management Complete Guide 2023
ArticleCAPM Exam – Difficulty, Details and Preparation Tips
ArticleWhat is Project Management?
ArticleIs it worth getting the CAPM certification?
ArticleIs PMP better than MBA?
ArticleWhat is PMI ACP certification?
ArticleIs PMP exam difficult?
ArticleIs PMI ACP worth it?
ArticlePMP or CAPM – which is better?
ArticleWhat is pass percentage for the CAPM exam?
ArticlePMP or PMI ACP – which certification should you get?
ArticlePMP Certification Cost Details
ArticleHow to get PMP certification - Guide 2022
ArticleHow to create an effective project plan
ArticleTop Project Manager Interview Questions and Answers 2022
ArticleGuide to Change Management for Organizational Transformation
ArticleResource Manager Interview Questions and Answers 2022
ArticleTop Project Manager Qualifications and Career Path in 2023
ArticleNetwork Diagram - Types, Topology and Use in Project Management
ArticleProject Management Life Cycle and Its Phases
ArticleGuide to Project Management Processes, Methodologies and Lifecycles
ArticleProcess Capability Analysis Explained
ArticleFinancial Risk and Its Types
ArticleConstruction Project Management - Roles, Stages and Benefits
ArticleRisk Management Strategies in Project Management
ArticleProject Management Principles - 12 Essentials
ArticleProject Management Framework Guide
ArticleStrategic Management Guide 2022
ArticleProject Management Books List - Best of 2022
ArticleProject Documentation and Its Importance
ebookProject Management Tips - Best of 2022
ArticleProject Management Apps Best of 2022
ArticleDigital Project Manager – Skills, Salary, and Scope
ArticleProject Communication Plan – How to Create and Use
ArticleEarned Value Management and Its Significance
ArticlePlanning Poker Estimation Technique
ArticleProject Management vs Product Management
ArticleProject Crashing in Project Management
ArticleProject Controlling and its Importance in Project Management
ArticleProject Report and its Significance in Project Management
ArticleProject Cost Management Guide 2022
ArticleProduct Lifecycle Management
ArticleProject Portfolio Management Guide
ArticleProgram Manager vs Project Manager - Comparison of Roles and Careers
ArticleWBS Dictionary - A Beginner's Guide
ArticleStakeholder Analysis and Stakeholder Management Guide
ArticleProject Management Phases Explained
ArticleProject Management Knowledge Areas
ArticleLeadership Theories for Managers
ArticlePMP Pass Rate in 2022 - Guide to Clear the PMP Exam
ArticleProject Schedule Management Guide for Beginners
ArticleProject Deliverables in Project Management
ArticleConflict Resolution in Project Management
ArticlePERT vs CPM in Project Management
ArticleGantt Charts - The Ultimate Guide
ArticleWork Breakdown Structure in Project Management
ArticleTop Gantt Chart Makers in 2022
ArticleGantt Chart Tools - Best of 2022
ArticleHow to create a work breakdown structure
ArticleProject Manager Resume Guide – Best Tips and Examples
ArticleProduct Management Frameworks - The Ultimate Guide 2022
ArticleProduct Planning - A Beginner's Guide
ArticleWhat is Product Management? - A Beginner's Guide
ArticleGuide to Project Stakeholder Management
ArticlePMP® Certification Salary: Job and Salary Scope in 2023
ArticleTop Project Engineer Skills
ArticleGuide to Technical Project Management
ArticleTop 10 project management competencies
ArticleNegotiation in Project Management: The Utimate Guide
ArticleTime Management in Project Management - Steps to Implement it
ArticleTop Program Manager Skills of Successful Program Managers
ArticleA Brief Guide to Conflict Management Approaches
ArticleWhat is a Risk Management Plan? A Comprehensive Guide
ArticleWorkflow Diagram - Steps to Create, Symbols, Types, and Uses
ArticleLast updated on Mar 13 2023
Last updated on Jan 4 2023
Last updated on Dec 27 2022
Last updated on Jan 23 2023
Last updated on Aug 29 2022
Last updated on Dec 27 2022